25% reduction in time
Our client required to update the living accommodation & facilities on their offshore asset to accommodate an increase in headcount for operational activities. whilst maintaining production. Through effective pull planning execution of work scope was reduced by 101 day, 25% improvement.
Mobilisations for Scaffolding reduced by 30%
The clients offshore personnel identified there were challenges when it came to organising scaffold for maintenance work across all its assets. The changes designed & implemented by the offshore team created a safer environment & allowed for predictable, efficient maintenance activities.