rig reliability

Rig Reliability

Back to Case Studies

The Opportunity

Our client experienced drilling rig delays, resulting in running 18.4 days behind drilling schedule. The delayed delivery of wells resulted in lost production, an opportunity of ~ 3.12mbeod / ~$219k in lost revenue each week.

Nonproductive time (NPT) was 18% versus a target of <2%, 50% of the engineering & operations teams time was consumed with hidden waste which if removed would allow them to perform scope that will help with rig reliability & therefore NPT.

Our client wanted to eliminate this waste for both the asset & teams, they identified the scoping, prioritisation, planning, scheduling & execution of all activities could potentially impact NPT.

Approach Taken

To address this, a cross-functional team from the drill rig were brought together to undertake a Value Stream Mapping (VSM) session. The issues identified during the VSM were Root Cause Analysed (RCA) & opportunities to improve or eliminate identified.

These opportunities were then worked by the same team during a 3 day Kaizen event, opportunities realised were: simplification of rig engineering processes & how they work, identify & prioritise simultaneous operations & drilling outage scopes, rationalise Planned Maintenance Routines, clarify rig down communication protocol, rig Engineering funding process reviewed & simplified & support timetable established, visual management system implemented for proactive prioritisation & delivery.

Benefits Realised

Improvement ideas implemented during the Kaizen Event gave 4968 hours back to business through more efficient use of rig engineering time. This time back enabled engineering to get a clear understanding of vulnerabilities & defects & provided the capacity to address these.

Drilling schedule now ahead of plan with NPT <=2%, cost avoidance of $496k through liquidation of project carry over & punch list scopes.

Reduction of non-productive time & bringing the drill schedule forward brought a $22.8m production revenue gain.

Increased morale of drilling & engineering teams through them being empowered to define & implement the improvements & also though the removal of frustration & delays.

Download PDF

(File Size: 330KB)

Rig Reliability

All Case Studies

Connect

email
LinkedIn
Twitter
Instagram
Facebook

© 2022 Practical Business Improvements.

  • Sitemap |
  • T&C's |
  • Privacy